Final Phase of the Goat Hill Stormwater Project?

It's been a rough winter. Our vehicles and bodies have taken a beating with the rough roads. We've navigated potholes, oversized speed bumps, uneven berms, catch basins, staging equipment and building materials. It's been a mess but our roads will soon be much improved, widened in places, drain better, and should be far safer. This construction project is over a year behind schedule but an end is finally in sight!

CURRENT PLAN

The City and OMA met onsite the week of May 12 to discuss the remaining work. Below is the plan as we know it as of mid-May.

SCHEDULE

OMA to restart work activities on June 9nd, 2025 and (hopefully) complete their work by September.

  1. NE 117th PL/midway: OMA restarts work activities on NE 117th PL. They will complete a few miscellaneous utility connections, install a new retaining wall, remove the 3 temporary drainage berms and repave.
  2. NE 116th PL/front-side: OMA then plans to move activities to NE 116th PL. apply the second layer of pavement. They also will address some minor storm drainage improvements for the natural springs that developed over winter. The City is still working with OMA to rebuild the retaining walls above the first blind corner.
  3. NE 120th St/backside: OMA removes their equipment, excess staging materials, and the 2 speed bumps/temporary drainage berms along NE 120th St.

A Our Kirkland Request for Service is the best way to communicate any concerns with this project.

CONTACTS

  • Brian Baker: (bbaker@kirklandwa.gov) is the current Project Engineering Manager
  • James Waihenya: Project Engineer resigned at the end of 2024.
  • Christian Knight: (cknight@kirklandwa.gov) remains as our Project Outreach focal
  • Rik Mayer: Construction Inspector

HISTORY

MORE INFO

PREVIOUS PLAN

Comments

Popular posts from this blog

Group Mailbox Relocation

UPDATED APRIL 21, 2026: The team attempting to move a portion of the mailboxes to the top-of-the-hill has disbanded. During this 5 month effort, we have been unable to find a location suitable to the residents, or that meet the safety standards of the Post Office and the City. Narrow road widths less than 20ft and limited sight distances are the primary obstacles. This does not make the problem go away. Our Postmaster, Michael Crimmins, acknowledges there's a safety issue for his drivers and would like to see a resolution. Vehicles navigating the hairpin turn apparently add difficulty when making mail deliveries. From a residents perspective, the plastic mailboxes are deprecated and a security risk. They should be replaced with newer, more secure, metal cluster boxes. The convenience of mailboxes located closer to our homes remains a desirable goal, especially to those at the top of the hill. Other considerations: residents have been asking the Kirkland Post Office to c...

Passing the Torch, Sharing the Light

All things must pass... and the good times must be celebrated! Goat Hill residents come and go but never has there been a shift quite like the present. Scott and Lisa, Dave and Mary, Andrea, Scuba and Adrian, and Nick and Candace all have either moved or are planning to move this spring. Soon the Doblers and Uta and Tovi will move on to their next adventures. Some will stay local. Some will move halfway around the world. All will be missed. One can't help but reflect on the many traditions we've enjoyed up here on The Hill. Easter egg hunts, Christmas parties, and the monthly First Friday gatherings make this place an incredibly special and unique place to live. One of the most enduring traditions has been the solstice firings, both winter and summer. Our artists in residence, Lisa Crubaugh and Scott Miller have carried this tradition from it's roots in Ballard where it was started by Regnor Reinholdtsen, to its current location at the top of Goat Hill. ...

Billy Goat Trail

UPDATE July 27, 2026: Progress has been challenging. The City has concerns with the steep slopes and has prioritized land acquisition over trail creation or improvement. It could take years if we wait for the City to move this important project forward. To hopefully expedite progress, the UW Green Futures Lab has been engaged to create a preliminary plan for the Billy Goat Trail that we can then present to the City. This should save time and money. A professional civil engineering firm would then be engaged to prepare plans for a trail and submitted for permits. Costs for this approach are not free. The Finn Hill Neighborhood Association has stepped up but yes, this will cost money. In 3-5 weeks, the UW Green Futures Lab should be able to find an acceptable path from Juanita Heights Park down to NE 120th St. It may be our social, neighbor-built trail, or they may find a better, more accessible path. There are two wetlands areas to negotiate and literally hundreds of steps to build....