Skip to main content

Posts

Showing posts from May, 2024

Puget Sound Energy’s planned night work

Puget Sound Energy will relocate their natural gas lines through the night from 5:00pm to 1:00am to make room for the new stormwater pipes being installed on Northeast 116th, 117th and 118th places. Work is proposed to begin June 3 and continue until August 8. The City hosted a Zoom meeting on May 30 to discuss the project. Video will be posted here once it becomes available. Current schedule: June 3 - 14 on NE 116th Place (Frontside closed) June 24 - July 25 on NE 116th, 117th and 118th Places (Frontside closed) July 26 - August 8 on NE 117th PL and 90th Ave NE (Backside closed)