Final Phase of the Goat Hill Stormwater Project?

It's been a rough winter. Our vehicles and bodies have taken a beating with the rough roads. We've navigated potholes, oversized speed bumps, uneven berms, catch basins, staging equipment and building materials. It's been a mess but our roads will soon be much improved, widened in places, drain better, and should be far safer. This construction project is over a year behind schedule but an end is finally in sight! CURRENT PLAN The City and OMA met onsite the week of May 12 to discuss the remaining work. Below is the plan as we know it as of mid-May. SCHEDULE OMA to restart work activities on June 9nd, 2025 and (hopefully) complete their work by September. NE 117th PL/midway: OMA restarts work activities on NE 117th PL. They will complete a few miscellaneous utility connections, install a new retaining wall, remove the 3 temporary drainage berms and repave. NE 116th PL/front-side: OMA then plans to move activities to NE 116th PL. apply the second layer of...