Skip to main content

Goat Hill Drainage Project

The City has begun construction on an over $3 million drainage management project on Goat Hill that will replace storm pipes, culverts and catch basins on sections of three streets. The 7 month long project will run from Spring 2024 - Fall 2024. The project will also stabilize an eroding drainage ditch with a rip-rap culvert crossing along Northeast 117th Place. You can learn more here.

Please drive carefully! There have been two construction related accidents so far!

August 19-23 Update: OMA reports that on 116th St (bottom of frontside to first hairpin), OMA will be ripping out the old pavement, laying down gravel, and repaving with an initial layer of asphalt. OMA has requested that the backside be used for uphill travellers and the frontside be used for traveling downhill.

August 12 Update: OMA is back to work. They have hired their own security personel.

August 1 Update: Contractor postpones stormwater work. Unfortunately OMA has received threats of violence and had damaged equipment. Kirkland Police investigated and issued a restraining order on the individual. PSE continues their evening work on the backside as planned.

June 7 Update: Goat Hill residents should expect road closures this week from 7 a.m. to 6 p.m. on Northeast 116th Place. Kirkland’s contractor is keeping open the Northeast 120th Place access to Goat Hill.

OMA Construction is allowed to work between 7 a.m. and 6 p.m.

Puget Sound Energy is working from 7 p.m. to 5 a.m.

May 29 Update: PSE is planning to work nights until August moving natual gas lines to make room for the new stormwater pipesbeing installed on Northeast 116th, 117th and 118th places. Learn more.

May 21 Update: Road closures this week will be from 9 a.m. to 3 p.m. on Northeast 116th Place. Kirkland’s contractor is keeping open the Northeast 120th Place access to Goat Hill.

May 10 Update: Road closures expected this week from 9 a.m. to 3 p.m. on Northeast 116th Place. Kirkland’s contractor is keeping open the "backside" open, Northeast 120th Place access to Goat Hill.

Residents concerns are here.

Kirkland’s Goat Hill stormwater drainage contractor began work in May that will improve stormwater drainage and slope stability on sections of Goat Hill by completing a variety of tasks aimed at slowing and consolidating stormwater.

The project will abandon an open ditch install along Northeast 117th Place, install 2,500 linear feet of new stormwater pipe along it, Northeast 116th Place and 90th Avenue Northeast. It will also install more than 50 catch-basins and a retaining wall.

This capital project is the second of two projects Kirkland planned to reduce flooding potential on Goat Hill.

The City hired OMA Construction in February 2024 to implement the design and plans to complete construction by October 2024.

The project will also stabilize an eroding drainage ditch with a rip-rap culvert crossing along Northeast 117th Place.

Residents Concerns/Suggestions shared with Christian Knight, Project Outreach 425-587-3831 :

  • Informational Signage: Signage at the group mailboxes would help inform folks of the project and website.
  • Directional Signage: Best to be placed at the mailboxes to inform drivers of the best way down.
  • Flaggers: Often ineffective as they stand out of sight or in locations that can't be seen until one of the hairpin turns has already been negotiated and the driver must then turn around.
  • Multiple Project Coordination: E.G. BEAU Construction finished replacing the retaining wall at the bottom of NE 117th P PL that had failed and will be paving the road again. The road will of course be torn up in the next few months for the larger stormwater drainage project. Perhaps the two back-to-back efforts could be coordinated to minimize disruption, detours and added expense of paving this section a third time in less than a year.
  • Communication: The building moratorium listserv may be something you could piggyback on to use for communicating with us.

We often struggle with getting our kids to school on time, attending appointments, etc. Any help you can provide will go a long way in making our commutes more efficient!

More information:

Streets Levy

Kirkland approved a Streets Levy in 2012 but possibly ended in 2020. Some good info on what was accomplished, unfortunately nothing for Goat Hill. 2012 Streets Levy

A "conceptual" street levy is being developed for June 2025. June 2025 Streets Levy

Last update August 13, 2024

Comments

Popular posts from this blog

Group Mailbox Relocation

UPDATED APRIL 21, 2026: The team attempting to move a portion of the mailboxes to the top-of-the-hill has disbanded. During this 5 month effort, we have been unable to find a location suitable to the residents, or that meet the safety standards of the Post Office and the City. Narrow road widths less than 20ft and limited sight distances are the primary obstacles. This does not make the problem go away. Our Postmaster, Michael Crimmins, acknowledges there's a safety issue for his drivers and would like to see a resolution. Vehicles navigating the hairpin turn apparently add difficulty when making mail deliveries. From a residents perspective, the plastic mailboxes are deprecated and a security risk. They should be replaced with newer, more secure, metal cluster boxes. The convenience of mailboxes located closer to our homes remains a desirable goal, especially to those at the top of the hill. Other considerations: residents have been asking the Kirkland Post Office to c...

Passing the Torch, Sharing the Light

All things must pass... and the good times must be celebrated! Goat Hill residents come and go but never has there been a shift quite like the present. Scott and Lisa, Dave and Mary, Andrea, Scuba and Adrian, and Nick and Candace all have either moved or are planning to move this spring. Soon the Doblers and Uta and Tovi will move on to their next adventures. Some will stay local. Some will move halfway around the world. All will be missed. One can't help but reflect on the many traditions we've enjoyed up here on The Hill. Easter egg hunts, Christmas parties, and the monthly First Friday gatherings make this place an incredibly special and unique place to live. One of the most enduring traditions has been the solstice firings, both winter and summer. Our artists in residence, Lisa Crubaugh and Scott Miller have carried this tradition from it's roots in Ballard where it was started by Regnor Reinholdtsen, to its current location at the top of Goat Hill. ...

Billy Goat Trail

UPDATE July 27, 2026: Progress has been challenging. The City has concerns with the steep slopes and has prioritized land acquisition over trail creation or improvement. It could take years if we wait for the City to move this important project forward. To hopefully expedite progress, the UW Green Futures Lab has been engaged to create a preliminary plan for the Billy Goat Trail that we can then present to the City. This should save time and money. A professional civil engineering firm would then be engaged to prepare plans for a trail and submitted for permits. Costs for this approach are not free. The Finn Hill Neighborhood Association has stepped up but yes, this will cost money. In 3-5 weeks, the UW Green Futures Lab should be able to find an acceptable path from Juanita Heights Park down to NE 120th St. It may be our social, neighbor-built trail, or they may find a better, more accessible path. There are two wetlands areas to negotiate and literally hundreds of steps to build....