Please drive carefully! There have been two construction related accidents so far!
August 19-23 Update: OMA reports that on 116th St (bottom of frontside to first hairpin), OMA will be ripping out the old pavement, laying down gravel, and repaving with an initial layer of asphalt. OMA has requested that the backside be used for uphill travellers and the frontside be used for traveling downhill.
August 12 Update: OMA is back to work. They have hired their own security personel.
August 1 Update: Contractor postpones stormwater work. Unfortunately OMA has received threats of violence and had damaged equipment. Kirkland Police investigated and issued a restraining order on the individual. PSE continues their evening work on the backside as planned.
June 7 Update: Goat Hill residents should expect road closures this week from 7 a.m. to 6 p.m. on Northeast 116th Place. Kirkland’s contractor is keeping open the Northeast 120th Place access to Goat Hill.
OMA Construction is allowed to work between 7 a.m. and 6 p.m.
Puget Sound Energy is working from 7 p.m. to 5 a.m.
May 29 Update: PSE is planning to work nights until August moving natual gas lines to make room for the new stormwater pipesbeing installed on Northeast 116th, 117th and 118th places. Learn more.
May 21 Update: Road closures this week will be from 9 a.m. to 3 p.m. on Northeast 116th Place. Kirkland’s contractor is keeping open the Northeast 120th Place access to Goat Hill.
May 10 Update: Road closures expected this week from 9 a.m. to 3 p.m. on Northeast 116th Place. Kirkland’s contractor is keeping open the "backside" open, Northeast 120th Place access to Goat Hill.
Residents concerns are here.
Kirkland’s Goat Hill stormwater drainage contractor began work in May that will improve stormwater drainage and slope stability on sections of Goat Hill by completing a variety of tasks aimed at slowing and consolidating stormwater.
The project will abandon an open ditch install along Northeast 117th Place, install 2,500 linear feet of new stormwater pipe along it, Northeast 116th Place and 90th Avenue Northeast. It will also install more than 50 catch-basins and a retaining wall.
This capital project is the second of two projects Kirkland planned to reduce flooding potential on Goat Hill.
The City hired OMA Construction in February 2024 to implement the design and plans to complete construction by October 2024.
The project will also stabilize an eroding drainage ditch with a rip-rap culvert crossing along Northeast 117th Place.
Residents Concerns/Suggestions shared with Christian Knight, Project Outreach 425-587-3831 :
- Informational Signage: Signage at the group mailboxes would help inform folks of the project and website.
- Directional Signage: Best to be placed at the mailboxes to inform drivers of the best way down.
- Flaggers: Often ineffective as they stand out of sight or in locations that can't be seen until one of the hairpin turns has already been negotiated and the driver must then turn around.
- Multiple Project Coordination: E.G. BEAU Construction finished replacing the retaining wall at the bottom of NE 117th P PL that had failed and will be paving the road again. The road will of course be torn up in the next few months for the larger stormwater drainage project. Perhaps the two back-to-back efforts could be coordinated to minimize disruption, detours and added expense of paving this section a third time in less than a year.
- Communication: The building moratorium listserv may be something you could piggyback on to use for communicating with us.
We often struggle with getting our kids to school on time, attending appointments, etc. Any help you can provide will go a long way in making our commutes more efficient!
More information:
- Final DETAILED Plans
- Project Map
- History of Capital Projects
- Kirkland Wetlands Overlay
- Our Kirkland Request for Service
Streets Levy
Kirkland approved a Streets Levy in 2012 but possibly ended in 2020. Some good info on what was accomplished, unfortunately nothing for Goat Hill. 2012 Streets Levy
A "conceptual" street levy is being developed for June 2025. June 2025 Streets Levy
Last update August 13, 2024